CUP: C86C20000020001
LAVORI DI RICOSTRUZIONE IMMOBILI PRIVATI IN CLASSE DI PRIORIT A - PEU 68 SP 02
SUMMARY OF THE PROJECT
LAVORI DI RICOSTRUZIONE IMMOBILI PRIVATI IN CLASSE DI PRIORIT A - PEU 68 SP 02
Implementation indicator
Volume oggetto di intervento
- Target
- 480 mc
- Achieved
- 480 mc
Download project
Funding monitored
€ 100,579.63
of which cohesion funds
€ 100,579.63
Given name | Amount |
---|---|
Development and Cohesion Fund | 100579.63 |
Payments monitored
€ 100,579.63
of which cohesion funds
€ 100,579.63
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2008 | 159.74 | 159.74 | 0 |
2009 | 0 | 159.74 | 0 |
2010 | 0 | 159.74 | 0 |
2011 | 0 | 159.74 | 0 |
2012 | 0 | 159.74 | 0 |
2013 | 0 | 159.74 | 0 |
2014 | 0 | 159.74 | 0 |
2015 | 0 | 159.74 | 0 |
2016 | 0 | 159.74 | 0 |
2017 | 0 | 159.74 | 0 |
2018 | 0 | 159.74 | 0 |
2019 | 0 | 159.74 | 0 |
2020 | 0 | 159.74 | 0 |
2021 | 0 | 159.74 | 0 |
2022 | 100419.89 | 100579.63 | 100 |
State of progress
Completed
Expected start: 30/11/2020
Effective start: 30/11/2020
Expected end: 22/03/2022
Effective end: 22/03/2022
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- COMUNE DI URURI
- Beneficiary
- CORBO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE MOLISE
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico