LAVORI DI COMPLETAMENTO DELLA RETE FOGNARIA TRA IL CAPOLUOGO E LA FRAZIONE TORE E ADEGUAMENTO IMPIANTO DI DEPURAZIONE.
SUMMARY OF THE PROJECT
LAVORI DI COMPLETAMENTO DELLA RETE FOGNARIA TRA IL CAPOLUOGO E LA FRAZIONE TORE E ADEGUAMENTO IMPIANTO DI DEPURAZIONE.
Implementation indicator
Portata media equivalente
- Target
- 1 mc/s
- Achieved
- 1 mc/s
Funding monitored
€ 996,000.00
of which cohesion funds
€ 996,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 996000.00 |
Payments monitored
€ 947,739.36
of which cohesion funds
€ 947,739.36
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 947739.36 | 947739.36 | 95 |
State of progress
Completed
Expected start: 01/06/2014
Effective start: 23/07/2018
Expected end: 31/05/2015
Effective end: 08/04/2019
Entities
- Planning body
- REGIONE CAMPANIA
- Implementing body
- REGIONE CAMPANIA
- Beneficiary
- REGIONE CAMPANIA
- Executor
- REGIONE CAMPANIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC CAMPANIA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche