CUP: E33H07000010009
CCAM - RIQUALIFICAZIONE SISTEMA ACQUEDOTTISTICO: ADDUZIONE DA MURISENGO A PENANGO E ADDUZIONE DA COSSOMBRATO A FRINCO.
SUMMARY OF THE PROJECT
CCAM - RIQUALIFICAZIONE SISTEMA ACQUEDOTTISTICO: ADDUZIONE DA MURISENGO A PENANGO E ADDUZIONE DA COSSOMBRATO A FRINCO.
Download project
Funding monitored
€ 4,056,138.20
of which cohesion funds
€ 536,800.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 536800.00 |
Region | 2500000.00 |
Another public source | 1019338.20 |
Payments monitored
€ 4,056,138.20
of which cohesion funds
€ 536,800.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2006 | 2976.20 | 2976.20 | 0 |
2007 | 102719.02 | 105695.22 | 2 |
2008 | 6441.50 | 112136.72 | 2 |
2009 | 7989.12 | 120125.84 | 2 |
2010 | 1114431.79 | 1234557.63 | 30 |
2011 | 1487932.93 | 2722490.56 | 67 |
2012 | 445870.53 | 3168361.09 | 78 |
2013 | 32137.98 | 3200499.07 | 78 |
2014 | 67999.66 | 3268498.73 | 80 |
2015 | 396027.66 | 3664526.39 | 90 |
2016 | 2379.66 | 3666906.05 | 90 |
2017 | 173922.16 | 3840828.21 | 94 |
2018 | 24931.50 | 3865759.71 | 95 |
2019 | 141402.07 | 4007161.78 | 98 |
2020 | 10072.77 | 4017234.55 | 99 |
2021 | 38903.65 | 4056138.20 | 100 |
State of progress
Completed
Expected start: 18/05/2010
Effective start: 18/05/2010
Expected end: 25/11/2020
Effective end: 25/11/2020
Entities
- Planning body
- REGIONE PIEMONTE
- Implementing body
- REGIONE PIEMONTE
- Beneficiary
- CONSORZIO DEI COMUNI PER L'ACQUEDOTTO DEL MONFERRATO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC PIEDMONT
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche