CUP: I58I05000020002
PROGETTO PER L'AMPLIAMENTO DEL SERBATOIO DELLA DIGA DI MACCHERONIS SUL FIUME POSADA
SUMMARY OF THE PROJECT
PROGETTO PER L'AMPLIAMENTO DEL SERBATOIO DELLA DIGA DI MACCHERONIS SUL FIUME POSADA
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Funding monitored
€ 21,391,422.48
of which cohesion funds
€ 12,911,422.48
Given name | Amount |
---|---|
Development and Cohesion Fund | 12911422.48 |
Region | 2480000.00 |
Another public source | 6000000.00 |
Payments monitored
€ 18,553,796.22
of which cohesion funds
€ 11,198,689.68
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2004 | 563853.46 | 563853.46 | 2 |
2005 | 12104.85 | 575958.31 | 2 |
2006 | 85866.18 | 661824.49 | 3 |
2007 | 1228230.05 | 1890054.54 | 8 |
2008 | 1133448.00 | 3023502.54 | 14 |
2009 | 3091911.00 | 6115413.54 | 28 |
2010 | 972288.51 | 7087702.05 | 33 |
2011 | 538942.00 | 7626644.05 | 35 |
2012 | 1387983.46 | 9014627.51 | 42 |
2013 | 492144.19 | 9506771.70 | 44 |
2014 | 84170.39 | 9590942.09 | 44 |
2015 | 148259.76 | 9739201.85 | 45 |
2016 | 245675.26 | 9984877.11 | 46 |
2017 | 219098.80 | 10203975.91 | 47 |
2018 | 1816574.11 | 12020550.02 | 56 |
2019 | 2109478.18 | 14130028.20 | 66 |
2020 | 1358367.05 | 15488395.25 | 72 |
2021 | 2361827.45 | 17850222.70 | 83 |
2022 | 703573.52 | 18553796.22 | 86 |
State of progress
Open
Expected start: 21/04/2006
Effective start: 21/04/2006
Expected end: 31/12/2023
Effective end: not available
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- CONSORZIO DI BONIFICA DELLA SARDEGNA CENTRALE
- Beneficiary
- CONSORZIO DI BONIFICA DELLA SARDEGNA CENTRALE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE SARDEGNA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche