CUP: J56J14000120002
ENTE PARCO NAZIONALE DOLOMITI BELLUNESI - REALIZZAZIONE DI UN SISTEMA SPERIMENTALE DI PROTEZIONE DELLA FAUNA SELVATICA
SUMMARY OF THE PROJECT
ENTE PARCO NAZIONALE DOLOMITI BELLUNESI - REALIZZAZIONE DI UN SISTEMA SPERIMENTALE DI PROTEZIONE DELLA FAUNA SELVATICA
Implementation indicator
Estensione dell'intervento in lunghezza
- Target
- 2,360 m
- Achieved
- 2,360 m
Funding monitored
€ 199,699.28
of which cohesion funds
€ 199,699.28
Given name | Amount |
---|---|
Development and Cohesion Fund | 199699.28 |
Payments monitored
€ 199,699.28
of which cohesion funds
€ 199,699.28
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 12859.49 | 12859.49 | 6 |
2016 | 181835.35 | 194694.84 | 97 |
2017 | 5004.44 | 199699.28 | 100 |
State of progress
Completed
Expected start: 05/05/2016
Effective start: 05/05/2016
Expected end: 05/07/2016
Effective end: 04/07/2016
Entities
- Planning body
- REGIONE DEL VENETO
- Implementing body
- REGIONE DEL VENETO
- Beneficiary
- REGIONE DEL VENETO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE VENETO
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Natura e biodiversita'