CUP: I49E11001320002
INTERVENTI URGENTI DI ADEGUAMENTO FUNZIONALE DELL'IMPIANTO DI SOLLEVAMENTO DI SANTA MARIA COGHINAS 2 DGR N.28/61 DEL 24.6.2011
Download project
Funding monitored
€ 1,112,028.69
of which cohesion funds
€ 1,150,000.00
Given name | Amount |
---|---|
European Union | 278007.17 |
Revolving Fund (National co-financing) | 558860.92 |
Region | 275160.60 |
- Economies:
- € 37,971.31
Payments monitored
€ 1,112,028.69
of which cohesion funds
€ 975,317.19
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2012 | 4990.95 | 4990.95 | 0 |
2013 | 15710.84 | 20701.79 | 1 |
2014 | 217447.71 | 238149.50 | 21 |
2015 | 873879.19 | 1112028.69 | 100 |
State of progress
Completed
Expected start: 01/11/2013
Effective start: 28/11/2013
Expected end: 01/07/2015
Effective end: 23/11/2015
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA
Theme
- Environment
- Gestione e distribuzione d'acqua (potabile)
Territory
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- ENTE ACQUE DELLA SARDEGNA ENAS
- Beneficiary
- ENTE ACQUE DELLA SARDEGNA ENAS
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
- Specific objective QSN
- Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali
Programming area
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Programme
- ROP RCE ERDF SARDINIA
- Axis
- Asse 4 Ambiente, Attrattività naturale, culturale e Turismo
- Operational objective
- Rafforzare il sistema di approvvigionamento idrico primario per gli usi multisettoriali.