CUP: G86C01000000001
SCIACCA - LAVORI DI REALIZZAZIONE DEL TRATTO TERMINALE DELLA BANCHINA DI RIVA NORD, DEI PIAZZALI RETROSTANTI ED OPERE DI ALAGGIO.
SUMMARY OF THE PROJECT
I LAVORI CONSISTONO NELLA RIQUALIFICAZIONE E L'ADEGUAMENTO DELLA BANCHINA DI RIVA, DELLO SCALO DI ALAGGIO E LA COSTRUZIONE DI UN MOTOSCALO DEL PORTO DI SCIACCA (AG)
Implementation indicator
Superficie oggetto di intervento
- Target
- 13,000 mq
- Achieved
- 0 mq
Funding monitored
€ 5,143,361.39
of which cohesion funds
€ 5,143,361.39
Given name | Amount |
---|---|
European Union | 4114689.12 |
Another public source | 1028672.27 |
- Economies:
- € 956,638.61
Payments monitored
€ 2,131,021.27
of which cohesion funds
€ 2,131,021.27
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 88802.07 | 88802.07 | 1 |
2020 | 1327194.29 | 1415996.36 | 27 |
2021 | 346524.91 | 1762521.27 | 34 |
2022 | 368500.00 | 2131021.27 | 41 |
State of progress
Open
Expected start: 02/07/2018
Effective start: 08/07/2020
Expected end: 31/12/2020
Effective end: not available
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- REGIONE SICILIANA
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF SICILY
- Axis
- Sistemi di Trasporto Sostenibili
- Specific objective
- AUMENTO DELLA COMPETITIVITÃ DEL SISTEMA PORTUALE E INTERPORTUALE