CUP: F27H17001240001
LAVORI DI SISTEMAZIONE DEL PIANO VIABILE AMMALORATO LUNGO LA SS 120 FRLL'ETNA E DELLE MADONIE IN TRATTI SALTUARI TRA IL 155+500 ED IL KM 215+627
SUMMARY OF THE PROJECT
RIPRISTINO DELLA PAVIMENTAZIONE STRADALE TRAMITE IL RIFACIMENTO DELLO STRATO D'USURA E DELLO STRATO DI BINDER E RIFACIMENTO DELLA SEGNALETICA ORIZZONTALE
Implementation indicators
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 27.20 km
- Achieved
- 27.20 km
Lunghezza totale delle strade ricostruite o rinnovate di cui: TEN-T
- Target
- 27.20 km
- Achieved
- 27.20 km
km di strade ristrutturate (core indicator n° 16)
- Target
- 27.20 km
- Achieved
- 27.20 km
- Slide 1
- Slide 2
- Slide 3
Download project
Funding monitored
€ 2,471,875.00
of which cohesion funds
€ 2,471,875.00
Given name | Amount |
---|---|
Another public source | 2471875.00 |
Payments monitored
€ 1,571,121.40
of which cohesion funds
€ 1,571,121.40
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 1344316.40 | 1344316.40 | 54 |
2019 | 226805.00 | 1571121.40 | 63 |
State of progress
Open
Expected start: 01/04/2018
Effective start: 21/06/2018
Expected end: 29/07/2018
Effective end: 29/07/2018
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- ANAS SOCIETA PER AZIONI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE SICILIANA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale