CUP: F24J17000170006
AZIONE 4.1.1 EFFICIENTAMENTO EDIFICIO DI VIA GIORDANO BRUNO - LIBERO CONSORZIO COMUNE DI RAGUSA
SUMMARY OF THE PROJECT
INTERVENTI PER L'EFFICIENTAMENTO ENERGETICO DELL'EDIFICIO CONSORTILE DI VIA GIORDANO BRUNO SN
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 118,034.13 KWh/a
- Achieved
- 118,034.10 KWh/a
Funding monitored
€ 502,907.21
of which cohesion funds
€ 502,907.21
Given name | Amount |
---|---|
European Union | 402325.77 |
Another public source | 100581.44 |
- Economies:
- € 97,092.79
Payments monitored
€ 463,980.93
of which cohesion funds
€ 463,980.93
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 9209.19 | 9209.19 | 1 |
2020 | 94314.79 | 103523.98 | 20 |
2021 | 360456.95 | 463980.93 | 92 |
State of progress
Open
Expected start: 01/12/2019
Effective start: 13/08/2020
Expected end: 30/11/2020
Effective end: 28/05/2021
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- LIBERO CONSORZIO COMUNALE DI RAGUSA
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF SICILY
- Axis
- ENERGIA SOSTENIBILE E QUALITA' DELLA VITA
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili