CUP: D78E13000010002
COMUNE - PEDARA - COMPLETAMENTO DELLA SCUOLA ELEMENTARE MONS. PENNISI SITA NELLA ZONA C1Z
SUMMARY OF THE PROJECT
IL PRESENTE INTERVENTO PREVEDE LA REALIZZAZIONE DI UN FABBRICATO IN SOSTITUZIONE DI QUELLO DA DEMOLIRE (0870340557) IN UN ALTRO SITO (VIA M. PENNISI)
Implementation indicator
Capacità dell'infrastruttura per l'assistenza all'infanzia o l'istruzione sostenuta
- Target
- 1 num
- Achieved
- 1 num
Funding monitored
€ 2,115,318.15
of which cohesion funds
€ 2,115,318.15
Given name | Amount |
---|---|
European Union | 1692254.52 |
Another public source | 423063.63 |
- Economies:
- € 34,681.85
Payments monitored
€ 182,350.77
of which cohesion funds
€ 182,350.77
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 182350.77 | 182350.77 | 8 |
State of progress
Open
Expected start: 01/07/2020
Effective start: 24/05/2021
Expected end: 04/12/2021
Effective end: 22/06/2023
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- COMUNE DI PEDARA
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF SICILY
- Axis
- Istruzione e Formazione
- Specific objective
- Aumento della propensione dei giovani a permanere nei contesti formativi e miglioramento della sicurezza e della fruibilità degli ambienti scolastici