CUP: D91J05000010001
REALIZZAZIONE DELLA CHIUSURA DELL'ANELLO FERROVIARIO DI PALERMO
SUMMARY OF THE PROJECT
REALIZZAZIONE DELLA CHIUSURA DELL'ANELLO FERROVIARIO DI PALERMO
Implementation indicator
Lunghezza totale delle linee tranviarie e metropolitane nuove o migliorate
- Target
- 1.70 km
- Achieved
- 0 km
Funding monitored
€ 152,095,271.02
of which cohesion funds
€ 152,095,271.02
Given name | Amount |
---|---|
European Union | 22393291.67 |
Municipality | 258000.00 |
Another public source | 83675322.92 |
Resources released | 45768656.43 |
Payments monitored
€ 95,767,698.49
of which cohesion funds
€ 95,767,698.49
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 29099672.41 | 29099672.41 | 19 |
2023 | 66668026.08 | 95767698.49 | 62 |
State of progress
Open
Expected start: 15/04/2014
Effective start: 24/07/2014
Expected end: 31/10/2022
Effective end: not available
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- COMUNE DI PALERMO
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF SICILY
- Axis
- ENERGIA SOSTENIBILE E QUALITA' DELLA VITA
- Specific objective
- AUMENTARE LA MOBILITÃ SOSTENIBILE NELLE AREE URBANE
Other projects in territory
Same theme
Same type of investment
SISTEMA TRAM CITTA' DI PALERMO | € 298,886,604 |
RADDOPPIO FERROVIARIO PALERMO - CARINI - TRATTA B - NOTABARTOLO - EMS/LA MALFA | € 290,894,000 |
SISTEMA TRAM PALERMO - FASE II | € 254,067,537 |
COMPLETAMENTO COLLETTORE FOGNARIO DELLA ZONA SUD-EST DI PALERMO. (33414) | € 47,313,795 |
SCMT SOTTOSISTEMA TERRA SICILIA | € 47,194,288 |