CUP: E71F11000080005
SAN FRATELLO (ME) - REALIZZAZIONE NUOVA ELISUPERFICIE
Download project
Funding monitored
€ 317,182.31
of which cohesion funds
€ 318,427.40
Given name | Amount |
---|---|
European Union | 237886.74 |
Status: other measures | 11347.20 |
Region | 67948.37 |
- Economies:
- € 82,817.69
Payments monitored
€ 317,182.31
of which cohesion funds
€ 317,182.51
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2012 | 119107.74 | 119107.74 | 37 |
2013 | 186401.37 | 305509.11 | 96 |
2014 | 11673.20 | 317182.31 | 100 |
State of progress
Completed
Expected start: 05/09/2012
Effective start: 05/09/2012
Expected end: 04/02/2013
Effective end: 27/03/2013
Type
- Infrastructure
- NUOVA REALIZZAZIONE
Theme
- Environment
- Prevenzione dei rischi (inclusa elaborazione e attuazione di piani e provvedimenti))
Territory
Entities
- Planning body
- REGIONE SICILIANA
- Implementing body
- COMUNE DI SAN FRATELLO
- Beneficiary
- COMUNE DI SAN FRATELLO
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
- Specific objective QSN
- Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali
Programming area
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Programme
- ROP CONV ERDF SICILY
- Axis
- Uso efficiente delle risorse naturali
- Operational objective
- Realizzare interventi infrastrutturali prioritari previsti nei PAI approvati, nella pianificazione di protezione civile e per la prevenzione e mitigazione dei rischi, anche ad integrazione di specifiche azioni del PRSR Sicilia.