CUP: I77F18000020007
RIQUALIFICAZIONE ENERGETICA DELLA SCUOLA SECONDARIA DI I GRADO G.PASCOLI DEL COMUNE DI CASTEL BOLOGNESE PER LA REALIZZAZIONE DI UN EDIFICIO NZEB
SUMMARY OF THE PROJECT
RIQUALIFICAZIONE ENERGETICA DELLA SCUOLA SECONDARIA DI I GRADO G.PASCOLI DEL COMUNE DI CASTEL BOLOGNESE PER LA REALIZZAZIONE DI UN EDIFICIO NZEB
Implementation indicator
Numero di azioni/progetti finanziati
- Target
- 1 num
- Achieved
- 1 num
Funding monitored
€ 1,132,182.23
of which cohesion funds
€ 277,971.38
Given name | Amount |
---|---|
Development and Cohesion Fund | 277971.38 |
Region | 61683.29 |
Municipality | 792527.56 |
- Economies:
- € 121,507.77
Payments monitored
€ 1,132,182.23
of which cohesion funds
€ 277,971.38
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 310546.53 | 310546.53 | 27 |
2022 | 0 | 310546.53 | 27 |
2023 | 821635.70 | 1132182.23 | 100 |
State of progress
Completed
Expected start: 03/06/2019
Effective start: 08/08/2018
Expected end: 10/09/2019
Effective end: 08/10/2020
Entities
- Planning body
- REGIONE EMILIA-ROMAGNA
- Beneficiary
- COMUNE DI CASTEL BOLOGNESE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC EMILIA-ROMAGNA
- Policy Area
- Energia
- Sector of intervention
- Efficienza energetica