Updated on 31/08/2019
Funding monitored € 677,011.00 of which cohesion funds € 2,053,974.43
Given name Amount
European Union318271.05
Revolving Fund (National co-financing)254616.83
Revolving Fund (Cohesion Action Plan)40468.93
Region63654.19
Economies:
€ 1,336,494.50
Payments monitored € 2,013,505.50 of which cohesion funds € 2,013,505.50
Year Amount Cumulative amount Percentage on public financing
2011145933.78145933.7821
20124437.17150370.9522
20131826.44152197.3922
2014350302.64502500.0374
20151470536.541973036.57291
201640468.932013505.50297

State of progress

Completed
Expected start: 01/04/2012
Effective start: 01/04/2012
Expected end: 31/12/2015
Effective end: 07/12/2015

Type

Theme

Territory

Entities

Planning body
REGIONE BASILICATA
Implementing body
AMMINISTRAZIONE PROVINCIALE DI MATERA
Beneficiary
AMMINISTRAZIONE PROVINCIALE DI MATERA
Priority QSN
Reti e collegamenti per la mobilità
General objective QSN
Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
Specific objective QSN
Contribuire alla realizzazione di un sistema logistico nazionale, supportando la costruzione di una rete nazionale di terminali di trasporto e di logistica, integrata, sicura, interconnessa ed omogenea

Programming area

2007-2013 Cohesion Action Plan
2007-2013 Cohesion Action Plan
Programme
PROGRAMMA PAC BASILICATA
Line
Salvaguardia
Action
Connettività viabilità interna alle reti TEN
European Regional Development Fund (ERDF)
2007-2013 EU Structural Funds
Programme
ROP CONV ERDF BASILICATA
Axis
Accessibilità
Operational objective
Completamento ed adeguamento delle direttrici strategiche a scala provinciale e regionale.