CUP: E52I19000090001
LAVORI DI EFFICIENTAMENTO ENERGETICO IMPIANTI DI PUBBLICA ILLUMINAZIONE IN BAISO CAPOLUOGO
SUMMARY OF THE PROJECT
LAVORI DI EFFICIENTAMENTO ENERGETICO ISTALLAZIONI DI CORPI ILLUMINANTI A LED, E RELAMPING
Implementation indicator
Riduzione annuale del consumo di energia
- Target
- 15 MW
- Achieved
- 16 MW
Funding monitored
€ 41,407.29
of which cohesion funds
€ 41,407.29
Given name | Amount |
---|---|
Development and Cohesion Fund | 41407.29 |
- Economies:
- € 8,592.71
Payments monitored
€ 41,407.29
of which cohesion funds
€ 41,407.29
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 41407.29 | 41407.29 | 100 |
State of progress
Completed
Expected start: 30/10/2019
Effective start: 30/10/2019
Expected end: 27/01/2020
Effective end: 21/01/2020
Entities
- Planning body
- COMUNE DI BAISO
- Beneficiary
- COMUNE DI BAISO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile