CUP: E75D19000070001
ABBATTIMENTO DELLE BARRIERE ARCHITETTONICHE E RIQUALIFICAZIONE ENERGETICA DELLA SEDE COMUNALE
SUMMARY OF THE PROJECT
OPERE EDILI E IMPIANTISTICHE
Implementation indicator
Numero di edifici pubblici con classificazione del consumo energetico migliorata
- Target
- 1 num
- Achieved
- 1 num
Funding monitored
€ 49,892.89
of which cohesion funds
€ 49,892.89
Given name | Amount |
---|---|
Development and Cohesion Fund | 49892.89 |
- Economies:
- € 107.11
Payments monitored
€ 26,274.38
of which cohesion funds
€ 26,274.38
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 26274.38 | 26274.38 | 52 |
State of progress
Open
Expected start: 25/10/2019
Effective start: 25/10/2019
Expected end: 18/12/2019
Effective end: 06/06/2020
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA PER ACCESSIBILITA' E ABBATTIMENTO DELLE BARRIERE ARCHITETTONICHE
Theme
Territory
Entities
- Planning body
- COMUNE DI CARREGA LIGURE
- Implementing body
- COMUNE DI CARREGA LIGURE
- Beneficiary
- COMUNE DI CARREGA LIGURE
- Executor
- ARQUATA COSTRUZIONI SRL
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile