CUP: I92J19007310001
EFFICIENTAMENTO ENERGETICO DEL PALAZZO COMUNALE CON L'INSTALLAZIONE DI PANNELLI FOTOVOLTAICI
SUMMARY OF THE PROJECT
EFFICIENTAMENTO ENERGETICO
Implementation indicator
Capacita' addizionale di produzione di energia da fonti rinnovabili
- Target
- 1 MW
- Achieved
- 1 MW
Funding monitored
€ 17,522.25
of which cohesion funds
€ 17,522.25
Given name | Amount |
---|---|
Development and Cohesion Fund | 17522.25 |
- Economies:
- € 309.98
Payments monitored
€ 17,522.25
of which cohesion funds
€ 17,522.25
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 16562.89 | 16562.89 | 94 |
2021 | 959.36 | 17522.25 | 100 |
State of progress
Completed
Expected start: 30/10/2019
Effective start: 08/06/2020
Expected end: 20/12/2019
Effective end: 19/10/2020
Entities
- Planning body
- COMUNE DI COLAZZA
- Beneficiary
- COMUNE DI COLAZZA
- Executor
- ELETTROIOLI SRL
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
ABBATTIMENTO BARRIERE ARCHITETTONICHE DEL PALAZZO COMUNALE ED EDIFICIO LIMITROFO | € 29,687 |