CUP: H52J19000270001
LAVORI DI RIQUALIFICAZIONE DEGLI IMPIANTI TERMICI A SERVIZIO DELL¿EDIFICIO SITO IN LOC. REPEN 86 (DOM ALBIN BUBNI¿)
SUMMARY OF THE PROJECT
LAVORI DI RIQUALIFICAZIONE DEGLI IMPIANTI TERMICI A SERVIZIO DELL¿EDIFICIO SITO IN LOC. REPEN 86 (DOM ALBIN BUBNI¿)
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 231.20 KWh/a
- Achieved
- 204.65 KWh/a
Download project
Funding monitored
€ 49,363.92
of which cohesion funds
€ 49,363.92
Given name | Amount |
---|---|
Development and Cohesion Fund | 49363.92 |
- Economies:
- € 636.08
Payments monitored
€ 49,363.92
of which cohesion funds
€ 49,363.92
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 45050.00 | 45050.00 | 91 |
2021 | 4313.92 | 49363.92 | 100 |
State of progress
Completed
Expected start: 31/10/2019
Effective start: 31/10/2019
Expected end: 31/12/2019
Effective end: 20/01/2020
Entities
- Planning body
- COMUNE DI MONRUPINO
- Beneficiary
- COMUNE DI MONRUPINO
- Executor
-
TERMOSYSTEM S.R.L.
ING. MARKO SAVRON
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile