CUP: I39E19001320001
NUOVO MANTO DI COPERTURA E COIBENTAZIONE SCUOLA PRIMARIA GARBATOLA
SUMMARY OF THE PROJECT
REALIZZAZIONE CON COIBENTAZIONE DI NUOVA GUAINA BITUMATA TETTO SCUOLA PRIMARIA DI GARBATOLA. SINTESI LAVORAZIONI ESAEGUITE:RIMOZIONE E DISFACIMENTO DELLA COPERTURA PIANA ESISTENTE , POSA DI PANNELLI TERMOISOLANTI, PREPARAZIONE PIANO DI POSA NUOVA GUAINA, FORMAZIONE DI MANTO IMPERMEABILE COSTITUITO DA DUE MEMBRANE ELASTOMERICHE, FISSAGGIO MECCANICO DELLA COPERTURA, OPERRE COMPLEMENTARI DI FINITURA.
Implementation indicator
Superficie coperta
- Target
- 800 mq
- Achieved
- 791 mq
Funding monitored
€ 86,108.88
of which cohesion funds
€ 86,108.88
Given name | Amount |
---|---|
Development and Cohesion Fund | 86108.88 |
- Economies:
- € 3,891.12
Payments monitored
€ 85,818.82
of which cohesion funds
€ 85,818.82
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 85818.82 | 85818.82 | 99 |
State of progress
Completed
Expected start: 30/10/2019
Effective start: 30/10/2019
Expected end: 28/01/2020
Effective end: 24/01/2020
Entities
- Planning body
- COMUNE DI NERVIANO
- Beneficiary
- COMUNE DI NERVIANO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile