CUP: E92G19000150005
LAVORI DI MANUTENZIONE STRAORDINARIA CON EFFICIENTAMENTO ENERGETICO PRESSO LA SCUOLA PRIMARIA IN LOCALITÃ LASSOLAZ
SUMMARY OF THE PROJECT
REALIZZAZIONE LAVORI DI MANUTENZIONE STRAORDINARIA CONSISTENTI NELLA COMPLETA SOSTITUZIONE DEI SERRAMENTI ESTERNI DELL¿EDIFICIO DI PROPRIETà COMUNALE CHE OSPITA LA SCUOLA PRIMARIA IN LOCALITà LASSOLAZ, QUALE INTERVENTO DI EFFICIENTAMENTO ENERGETICO
Implementation indicator
Numero di edifici pubblici con classificazione del consumo energetico migliorata
- Target
- 1 num
- Achieved
- 1 num
Funding monitored
€ 63,347.13
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 50000.00 |
Municipality | 13347.13 |
- Economies:
- € 3,299.03
Payments monitored
€ 63,347.13
of which cohesion funds
€ 50,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 44383.89 | 44383.89 | 70 |
2020 | 18963.24 | 63347.13 | 100 |
State of progress
Completed
Expected start: 18/10/2019
Effective start: 18/10/2019
Expected end: 16/02/2020
Effective end: 15/02/2020
Entities
- Planning body
- COMUNE DI PONTEY
- Beneficiary
- COMUNE DI PONTEY
- Executor
-
ING. LAVOYER MANUEL
CTS DOORS SRL
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile