CUP: G91B19000540005
FORNITURA ED INSTALLAZIONE IMPIANTO FOTOVOLTAICO SUL MUNICIPIO
SUMMARY OF THE PROJECT
INSTALLAZIONE IMPIANTO FOTOVOLTAICO
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 24,000 KWh/a
- Achieved
- 2,400 KWh/a
Funding monitored
€ 24,035.52
of which cohesion funds
€ 24,035.52
Given name | Amount |
---|---|
Development and Cohesion Fund | 24035.52 |
- Economies:
- € 3,964.60
Payments monitored
€ 24,035.52
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 24035.52 | 24035.52 | 100 |
State of progress
Completed
Expected start: 25/10/2019
Effective start: 25/10/2019
Expected end: 06/04/2021
Effective end: 06/04/2021
Entities
- Planning body
- COMUNE DI ROMALLO
- Beneficiary
- COMUNE DI NOVELLA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile