CUP: J22G19000370001
LAVORI DI ¿RIQUALIFICAZIONE ED EFFICIENTAMENTO ENERGETICO DELLA PALESTRA "SCUOLA PRIMARIA - ISTITUTO COMPRENSIVO AUTONOMO"
SUMMARY OF THE PROJECT
IL PROGETTO PREVEDE LA SOSTITUZIONE DEGLI INFISSI, L'INSTALLAZIONE DI UN SOLARE TERMICO, LA SOSTITUZIONE PARTE DI LINOLEUM, PULITURA E TINTEGGIATURA
Implementation indicator
Numero edifici scolastici oggetto dell'intervento
- Target
- 1 num
- Achieved
- 1 num
Funding monitored
€ 63,603.25
of which cohesion funds
€ 63,603.25
Given name | Amount |
---|---|
Development and Cohesion Fund | 63603.25 |
- Economies:
- € 6,396.75
Payments monitored
€ 31,391.90
of which cohesion funds
€ 31,391.90
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 31391.90 | 31391.90 | 49 |
State of progress
Open
Expected start: 31/10/2019
Effective start: 31/10/2019
Expected end: 23/02/2020
Effective end: 09/06/2020
Entities
- Planning body
- COMUNE DI CASAPESENNA
- Implementing body
- COMUNE DI CASAPESENNA
- Beneficiary
- COMUNE DI CASAPESENNA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile