CUP: D22E23000060001
EFFICIENTAMENTO ENERGETICO DI VIALE DON MINZONI CESENATICO
SUMMARY OF THE PROJECT
EFFICIENTAMENTO ENERGETICO DI VIALE DON MINZONI CESENATICO
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 36,018 KWh/a
- Achieved
- 0 KWh/a
Funding monitored
€ 107,355.51
of which cohesion funds
€ 107,355.51
Given name | Amount |
---|---|
European Union | 107355.51 |
Payments monitored
€ 104,871.20
of which cohesion funds
€ 104,871.20
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 104871.20 | 104871.20 | 97 |
State of progress
Completed
Expected start: 03/04/2023
Effective start: 03/04/2023
Expected end: 30/06/2023
Effective end: 30/08/2023
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- COMUNE DI CESENATICO
- Beneficiary
- COMUNE DI CESENATICO
- Executor
- COMUNE DI CESENATICO
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- NOP ERDF ENTERPRISES AND COMPETITIVENESS
- Axis
- Promuovere il superamento degli effetti della crisi nel cont
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili