CUP: C82E22000480001
EFFICIENTAMENTO ENERGETICO DI FRAZIONE PERTICARO
SUMMARY OF THE PROJECT
EFFICIENTAMENTO ENERGETICO DI FRAZIONE PERTICARO
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 35,097.75 KWh/a
- Achieved
- 35,097.75 KWh/a
Download project
Funding monitored
€ 134,322.00
of which cohesion funds
€ 134,322.00
Given name | Amount |
---|---|
European Union | 134322.00 |
Payments monitored
€ 134,322.00
of which cohesion funds
€ 134,322.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 134322.00 | 134322.00 | 100 |
State of progress
Completed
Expected start: 20/02/2023
Effective start: 28/08/2023
Expected end: 15/06/2023
Effective end: 20/09/2023
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- COMUNE DI UMBRIATICO
- Beneficiary
- COMUNE DI UMBRIATICO
- Executor
- COMUNE DI UMBRIATICO
Programming area
- Programme
- NOP ERDF ENTERPRISES AND COMPETITIVENESS
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 134,322.00
- Payments on cohesion funds
- € 134,322.00
- Axis
- Promuovere il superamento degli effetti della crisi nel cont
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili