MANUTENZIONE STRAORDINARIA PER EFFICIENTAMENTO ENERGETICO SCUOLASECONDARIA DI I GRADO 'ENRICO FERMI'
SUMMARY OF THE PROJECT
MANUTENZIONE STRAORDINARIA PER EFFICIENTAMENTO ENERGETICO SCUOLASECONDARIA DI I GRADO 'ENRICO FERMI'
Implementation indicator
Imprese beneficiate
- Target
- 6 num
- Achieved
- 6 num
Download project
Funding monitored
€ 738,206.32
of which cohesion funds
€ 583,411.69
Given name | Amount |
---|---|
Development and Cohesion Fund | 583411.69 |
Municipality | 154794.63 |
- Economies:
- € 259,086.48
Payments monitored
€ 671,162.00
of which cohesion funds
€ 583,411.69
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2017 | 607520.00 | 607520.00 | 82 |
2018 | 63642.00 | 671162.00 | 90 |
State of progress
Open
Expected start: 02/05/2017
Effective start: 02/05/2017
Expected end: 31/12/2017
Effective end: 21/12/2017
Entities
- Planning body
- MIUR ISTRUZIONE
- Implementing body
- COMUNE DI LURAGO D'ERBA
- Beneficiary
- COMUNE DI LURAGO D'ERBA
- Executor
- COMUNE DI LURAGO D'ERBA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELL'ISTRUZIONE E DEL MERITO
- Policy Area
- Istruzione e Formazione
- Sector of intervention
- Strutture educative e formative