ADEGUAMENTO STRUTTURALE PER LA MESSA IN ESERCIZIO DELLA SCUOLA MEDIA 'E. FERMI': COMPLETAMENTO E RIPRISTINO OPERE CIVILIEDILI ED ADEGUAMENTO IMPIANTI
SUMMARY OF THE PROJECT
ADEGUAMENTO STRUTTURALE PER LA MESSA IN ESERCIZIO DELLA SCUOLA MEDIA 'E. FERMI': COMPLETAMENTO E RIPRISTINO OPERE CIVILIEDILI ED ADEGUAMENTO IMPIANTI
Implementation indicator
Imprese beneficiate
- Target
- 2 num
- Achieved
- 2 num
Funding monitored
€ 3,294,886.53
of which cohesion funds
€ 3,294,886.53
Given name | Amount |
---|---|
Development and Cohesion Fund | 3294886.53 |
- Economies:
- € 151,426.83
Payments monitored
€ 3,259,045.19
of which cohesion funds
€ 3,259,045.19
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 634346.89 | 634346.89 | 19 |
2016 | 2229958.86 | 2864305.75 | 86 |
2017 | 378816.27 | 3243122.02 | 98 |
2018 | 15923.17 | 3259045.19 | 98 |
State of progress
Completed
Expected start: 15/04/2015
Effective start: 15/04/2015
Expected end: 17/11/2015
Effective end: 08/03/2017
Entities
- Planning body
- MIUR ISTRUZIONE
- Implementing body
- COMUNE DI LICODIA EUBEA
- Beneficiary
- COMUNE DI LICODIA EUBEA
- Executor
- COMUNE DI LICODIA EUBEA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELL'ISTRUZIONE E DEL MERITO
- Policy Area
- Istruzione e Formazione
- Sector of intervention
- Strutture educative e formative