CUP: D13I18000150006
STADIO CON PISTA DI ATLETICA E TRIBUNE
SUMMARY OF THE PROJECT
LAVORI DI COMPLETAMENTO DELLO STADIO A SERVIZIO DELLA NUOVA SCUOLA MARESCIALLI E BRIGADIERI DELL¿ARMA DEI CARABINIERI ¿FELICE MARITANO¿ IN FIRENZE, LOCALITà CASTELLO
Implementation indicator
Superficie oggetto di intervento
- Target
- 13,590 mq
- Achieved
- 13,590 mq
Funding monitored
€ 2,800,000.00
of which cohesion funds
€ 2,500,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 2500000.00 |
Another public source | 300000.00 |
Payments monitored
€ 2,492,770.67
of which cohesion funds
€ 2,250,000.67
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 675730.00 | 675730.00 | 24 |
2021 | 1378969.03 | 2054699.03 | 73 |
2022 | 422806.00 | 2477505.03 | 88 |
2023 | 15265.64 | 2492770.67 | 89 |
State of progress
Open
Expected start: 20/09/2020
Effective start: 04/08/2020
Expected end: 20/10/2021
Effective end: 15/06/2022
Entities
- Planning body
- ARMA CARABINIERI
- Implementing body
- PROVV.TO OO.PP. TOSCANA MARCHE UMBRIA
- Beneficiary
- ARMA CARABINIERI
Programming area
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Programme
- IMPIANTI SPORTIVI PER GRUPPI SPORTIVI MILITARI
- Line
- Infrastrutture
- Action
- Infrastrutture pubbliche, didattiche/universitarie, sociali e sanitarie
Other projects in territory
Same theme
Same type of investment
REALIZZAZIONE TRAMVIA NELL'AREA METROPOLITANA FIORENTINA | € 406,558,409 |
SISTEMA TRAMVIARIO LINEA 4 - LEOPOLDA - PIAGGE | € 169,550,000 |
PARCO DELLA MUSICA - REALIZZAZIONE I LOTTO: SALA GRANDE / TEATRO LIRICO | € 156,362,796 |
NUOVO TEATRO DELL'OPERA DI FIRENZE II STRALCIO 1?LOTTO | € 45,323,476 |
ADEGUAMENTO IDRAULICO DEL TORRENTE MUGNONE. | € 45,283,349 |