CUP: G81B07000300007
SSV. FONDO VALLE TAMMARO ¿ S.CROCE DEL SANNIO ¿ CASTELPAGANO - COLLE S. (1° LOTTO) - I STRALCIO FUNZIONALE - II STRALCIO FUNZIONALE
SUMMARY OF THE PROJECT
SSV. FONDO VALLE TAMMARO ¿ S.CROCE DEL SANNIO ¿ CASTELPAGANO - COLLE S. (1° LOTTO) - I STRALCIO FUNZIONALE - II STRALCIO FUNZIONALE
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 6.50 km
- Achieved
- 0 km
Funding monitored
€ 24,170,000.00
of which cohesion funds
€ 24,170,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 24170000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Not started
Expected start: 30/09/2019
Effective start: not available
Expected end: 31/03/2022
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- COMUNITA MONTANA TITERNO E ALTO TAMMARO
- Beneficiary
- REGIONE CAMPANIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale