CUP: J11H03000180001
POTENZIAMENTO FIUMETORTO LERCARA FRIDDI - PRIMA FASE FUNZIONALE
SUMMARY OF THE PROJECT
GLI INTERVENTI SI INQUADRANO NEL PIù AMPIO PROGETTO DI REALIZZAZIONE DEL COLLEGAMENTO VELOCE TRA PALERMO E CATANIA E CONSISTONO NELLA COSTRUZIONE DI UN NUOVO BINARIO VELOCE TRA FIUMETORTO E MONTEMAGGIORE. GLI INTERVENTI CONSENTIRANNO IL MIGLIORAMENTO DEI COLLEGAMENTI LUNGO LE DIRETTRICI PALERMO¿AGRIGENTO E PALERMO¿ CALTANISSETTA¿ENNA¿CATANIA.
Implementation indicator
Lunghezza totale delle linee ferroviarie ricostruite o rinnovate
- Target
- 17 km
- Achieved
- 0 km
Funding monitored
€ 1,849,805,468.60
of which cohesion funds
€ 350,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 350000000.00 |
Another public source | 1499805468.60 |
Payments monitored
€ 12,163,183.46
of which cohesion funds
€ 12,136,868.46
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 1529057.25 | 1529057.25 | 0 |
2019 | 0 | 1529057.25 | 0 |
2020 | 9407991.85 | 10937049.10 | 0 |
2021 | 1226134.36 | 12163183.46 | 0 |
State of progress
Open
Expected start: 26/10/2023
Effective start: 26/10/2023
Expected end: 09/07/2030
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- RETE FERROVIARIA ITALIANA SPA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto ferroviario