CUP: J19G01000000001
VARIANTE SU NUOVA SEDE PER L'ELIMINAZIONE DI PASSAGGI A LIVELLO IN COMUNE DI VILLANOVA SULL'ARDA
SUMMARY OF THE PROJECT
L¿INTERVENTO, DA REALIZZARSI CON IL CONCORSO FINANZIARIO DI RFI, PREVEDE LA REALIZZAZIONE DI UN ATTRAVERSAMENTO A LIVELLI SFALSATI DELLA LINEA FERROVIARIA FIDENZA ¿ CREMONA IN VARIANTE ALL¿ATTUALE TRACCIATO E CONSENTIRà L¿ELIMINAZIONE DEI PASSAGGI A LIVELLO IN COMUNE DI VILLANOVA. QUESTI INFATTI COMPORTANO NOTEVOLI RISCHI PER LA SICUREZZA DELLA CIRCOLAZIONE STRADALE E FERROVIARIA, OLTRE CHE CONSISTENTI RITARDI E RILEVANTI DISAGI.
Implementation indicator
Lunghezza totale delle linee ferroviarie ricostruite o rinnovate
- Target
- 3 km
- Achieved
- 0 km
Download project
Funding monitored
€ 12,701,980.20
of which cohesion funds
€ 3,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 3000000.00 |
Another public source | 9701980.20 |
- Other resources - To be found:
- € 2,161,543
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 31/12/2024
Effective start: not available
Expected end: 17/02/2027
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- RETE FERROVIARIA ITALIANA SPA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto ferroviario