CUP: D19J21004760001
LINEA 1 - MIGRAZIONE SISTEMA E ROTABILE
SUMMARY OF THE PROJECT
SERVIZI DI MIGRAZIONE DAL SISTEMA ANALOGICO VAL DI SEGNALAMENTO DELLA LINEA 1 DELLA METROPOLITANA AUTOMATICA DI TORINO AD UN SISTEMA DI SEGNALAMENTO DIGITALE BASATO SULLA TECNOLOGIA CBCT, FORNITURA DI 16 NUOVI TRENI COMPATIBILI CON IL SISTEMA VAL 208, FORNITURA E INSTALLAZIONE DI NUOVI AUTOMATISMI IMBARCATI SUI VEICOLI IN ESERCIZIO VAL 208NG
Implementation indicator
Lunghezza totale delle linee tranviarie e metropolitane nuove o migliorate
- Target
- 1 km
- Achieved
- 0 km
Funding monitored
€ 71,200,000.00
of which cohesion funds
€ 71,200,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 71200000.00 |
Payments monitored
€ 16,199,895.26
of which cohesion funds
€ 16,199,895.26
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 16199895.26 | 16199895.26 | 22 |
State of progress
Open
Expected start: 04/02/2022
Effective start: 04/02/2022
Expected end: 28/02/2025
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- INFRATRASPORTITO SRL
- Beneficiary
- COMUNE DI TORINO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Mobilita' urbana