CUP: F19J14001910001
LAVORI DI MANUTENZIONE STRAORDINARIA PER L'ADEGUAMENTO DELLE BARRIERE STRADALI LUNGO LE STRADE STATALI DEL C.M. B DI IGLESIAS IN T.S.
SUMMARY OF THE PROJECT
LAVORI DI MANUTENZIONE STRAORDINARIA PER L'ADEGUAMENTO DELLE BARRIERE STRADALI LUNGO LE STRADE STATALI DEL C.M. B DI IGLESIAS IN T.S.
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 0 km
Funding monitored
€ 2,115,223.84
of which cohesion funds
€ 2,115,223.84
Given name | Amount |
---|---|
Development and Cohesion Fund | 2115223.84 |
Payments monitored
€ 39,242.85
of which cohesion funds
€ 14,242.85
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 14242.85 | 14242.85 | 0 |
2021 | 25000.00 | 39242.85 | 1 |
State of progress
Open
Expected start: 05/02/2024
Effective start: not available
Expected end: 24/07/2024
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- ANAS SOCIETA PER AZIONI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico