CUP: J47H19001770002
S.P. N. 82 DI MONTALENGHE DAL KM 6+300 AL KM 7+000, DAL KM 7+600 AL KM 8+600 E DAL KM 9+000 AL KM 10+000. S.P. N. 81 DI MAZZÊ DIR.03 DAL KM 0+000 AL KM 0+400. INTERVENTI DI RIPRISTINO DELLA SOVRASTRUTTURA STRADALE A TRATTI SALTUARI.
SUMMARY OF THE PROJECT
TRATTASI DI INTERVENTO DI MANUTENZIONE STRAORDINARIA FINALIZZATO ALLA SISTEMAZIONE DELLA PAVIMENTAZIONE STRADALE ALL'INTERNO DEI TRATTI INDICATI
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 2.50 km
- Achieved
- 2.50 km
Download project
Funding monitored
€ 174,773.87
of which cohesion funds
€ 174,773.87
Given name | Amount |
---|---|
Development and Cohesion Fund | 174773.87 |
Payments monitored
€ 174,773.87
of which cohesion funds
€ 174,773.87
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 172068.37 | 172068.37 | 98 |
2021 | 798.84 | 172867.21 | 98 |
2022 | 1906.66 | 174773.87 | 100 |
State of progress
Completed
Expected start: 14/09/2020
Effective start: 14/09/2020
Expected end: 30/09/2020
Effective end: 30/09/2020
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- CITTA METROPOLITANA DI TORINO
- Beneficiary
- REGIONE PIEMONTE
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 174,773.87
- Payments on cohesion funds
- € 174,773.87
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico