CUP: D17H18002370001
S.P. N. 32 "BOCA - GRIGNASCO" AL KM 4+500 - S.P. N. 20 "AGNELLENGO - BARENGO - FARA NOVARESE"AL KM 3+000. MANUTENZIONE STRAORDINARIA DEI PONTI
SUMMARY OF THE PROJECT
RIFACIMENTO DEI MANUFATTI ESISTENTI MEDIANTE LA DEMOLIZIONE E LA RICOSTRUZIONE DEI MURO DI CONTENIMENTO E DELLA STRUTTURA PORTANTE. RIPRISTINO DELLA PAVIMENTAZIONE STRADALE, DEI PARAPETTI E DELLE BARRIERE DI PROTEZIONE.
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 1 km
Download project
Funding monitored
€ 215,000.00
of which cohesion funds
€ 200,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 200000.00 |
Province | 15000.00 |
Payments monitored
€ 198,661.26
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 10150.40 | 10150.40 | 4 |
2021 | 188510.86 | 198661.26 | 92 |
State of progress
Open
Expected start: 01/03/2021
Effective start: 01/03/2021
Expected end: 01/06/2021
Effective end: 01/06/2021
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI NOVARA
- Beneficiary
- REGIONE PIEMONTE
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 200,000.00
- Payments on cohesion funds
- € 0.00
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico