CUP: D22J15000000005
SISTEMAZIONE IDROGEOLOGICA E MESSA IN SICUREZZA RIO VALASSA A DIFESA DELL'ATTRAVERSAMENTO SULLA STRADA DEI MONTI
SUMMARY OF THE PROJECT
NUOVA COSTRUZIONE DI PONTICELLO SUL RIO VALASSA IN SOSTITUZIONE DELL¿ATTUALE ATTRAVERSAMENTO E REALIZZAZIONE DI SCOGLIERE LUNGO LE SPONDE DEL RIO, A MONTE A VALLE DEL NUOVO ATTRAVERSAMENTO, PER REGIMAZIONE ACQUE, PROTEZIONE SPONDE E MESSA IN SICUREZZA DELLA STRADA COMUNALE.
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 1 km
Download project
Funding monitored
€ 230,000.00
of which cohesion funds
€ 230,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 230000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Not started
Expected start: 01/07/2021
Effective start: 28/02/2022
Expected end: 30/08/2022
Effective end: 22/07/2022
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- COMUNE DI VAL DI CHY
- Beneficiary
- REGIONE PIEMONTE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico