CUP: C64E21001030001
FSC 2014/2020. PIANO OPERATIVO INFRASTRUTTURE (ART.1,CO.703,LETT.CDELLA L. N°190/2014) APPROVATO CON DELIBERA CIPE N. 12/2018. INTERVENTO "PORTO DI GIULIANOVA - INTERVENTI PER LA MESSA IN SICUREZZA DELL'ATTUALE IMBOCCATURA PORTUALE"
SUMMARY OF THE PROJECT
INTERVENTI PER LA MESSA IN SICUREZZA DELL'ATTUALE IMBOCCATURA PORTUALE: COMPLETAMENTO MOLO NORD, RIPARAZIONE MOLO SUD, PROTEZIONE CATODICA "MOLO LAUDADIO"
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 3,800,000 num
- Achieved
- 0 num
Funding monitored
€ 3,800,000.00
of which cohesion funds
€ 3,800,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 3800000.00 |
Payments monitored
€ 146,277.92
of which cohesion funds
€ 146,277.92
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 62446.76 | 62446.76 | 1 |
2023 | 83831.16 | 146277.92 | 3 |
State of progress
Open
Expected start: 31/08/2023
Effective start: not available
Expected end: 31/03/2024
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- REGIONE ABRUZZO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto marittimo