Updated on 30/06/2024
Funding monitored € 2,168,000.00 of which cohesion funds € 2,168,000.00
Given name Amount
European Union921400.00
Revolving Fund644980.00
Region276420.00
Another public source325200.00
Payments monitored € 2,167,988.20 of which cohesion funds € 2,167,988.20
Year Amount Cumulative amount Percentage on public financing
2021251804.79251804.7911
2022479405.27731210.0633
20231436778.142167988.2099

State of progress

Settled
Expected start: 19/01/2021
Effective start: 19/01/2021
Expected end: 30/06/2022
Effective end: not available

Entities

Planning body
PROVINCIA AUTONOMA DI BOLZANO
Beneficiary
INFORMATICA ALTO ADIGE SPA

Programming area

European Regional Development Fund (ERDF)
2014-2020 EU Structural Funds
Programme
ROP ERDF AP BOLZEN
Axis
CONTESTO DIGITALE
Specific objective
Digitalizzazione dei processi amministrativi e diffusione di servizi digitali pienamente interoperabili

Other projects in territory