Updated on 31/12/2020
Funding monitored € 453,538.53 of which cohesion funds € 350,000.00
Given name Amount
European Union71408.22
Revolving Fund (National co-financing)106148.77
Municipality275981.54
Economies:
€ 32,242.01
Payments monitored € 453,538.53 of which cohesion funds € 296,211.70
Year Amount Cumulative amount Percentage on public financing
20076000.006000.001
2008151326.83157326.8334
20090157326.8334
20102000.00159326.8335
2011197995.38357322.2178
201296216.32453538.53100

State of progress

Completed
Expected start: 23/10/2007
Effective start: 23/10/2007
Expected end: 31/12/2012
Effective end: 21/09/2012

Type

Theme

Territory

Entities

Planning body
REGIONE TOSCANA
Implementing body
COMUNE DI CASTEL DEL PIANO
Beneficiary
COMUNE DI CASTEL DEL PIANO
Priority QSN
Valorizzazione delle risorse naturali e culturali per l'attrattività e lo sviluppo
General objective QSN
Valorizzare le risorse naturali, culturali e paesaggistiche locali, trasformandole in vantaggio competitivo per aumentare l'attrattività, anche turistica, del territorio, migliorare la qualità della vita dei residenti e promuovere nuove forme di sviluppo economico sostenibile
Specific objective QSN
Aumentare in maniera sostenibile la competitività internazionale delle destinazioni turistiche delle Regioni italiane, migliorando la qualità dell'offerta e l'orientamento al mercato dei pacchetti turistici territoriali e valorizzando gli specifici vantaggi competitivi locali, in primo luogo le risorse naturali e culturali

Programming area

European Regional Development Fund (ERDF)
2007-2013 EU Structural Funds
Programme
ROP RCE ERDF TUSCANY
Axis
Valorizzazione risorse endogene sviluppo territ. sost.
Operational objective
Sostenere il superamento delle difficoltà  delle zone svantaggiate mediante sviluppo delle attività  economiche, tutela, valorizzazione e promozione delle risorse naturali e culturali, ai fini dello sviluppo di un turismo sostenibile.

Other projects in territory