CUP: F23F08000010002
AMPLIAMENTO E COMPLETAMENTO AREA P.I.P. - COMUNE DI PIGNOLA
Funding monitored
€ 794,062.57
of which cohesion funds
€ 800,000.00
Given name | Amount |
---|---|
European Union | 424081.33 |
Revolving Fund (National co-financing) | 295984.99 |
Region | 73996.25 |
- Economies:
- € 5,937.43
Payments monitored
€ 794,062.57
of which cohesion funds
€ 794,062.57
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2010 | 126589.28 | 126589.28 | 15 |
2011 | 479397.42 | 605986.70 | 76 |
2012 | 74711.36 | 680698.06 | 85 |
2013 | 61369.93 | 742067.99 | 93 |
2014 | 0 | 742067.99 | 93 |
2015 | 51994.58 | 794062.57 | 100 |
State of progress
Completed
Expected start: 21/06/2010
Effective start: 21/06/2010
Expected end: 15/06/2011
Effective end: 03/08/2012
Type
- Infrastructure
- NUOVA REALIZZAZIONE
Theme
- Energy
- Efficienza dell'energia, cogenerazione, gestione dell'energia
Territory
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- COMUNE DI PIGNOLA
- Beneficiary
- COMUNE DI PIGNOLA
- Priority QSN
- Competitività dei sistemi produttivi e occupazione
- General objective QSN
- Promuovere processi sostenibili e inclusivi di innovazione e sviluppo imprenditoriale
- Specific objective QSN
- Migliorare l'efficacia dei servizi alle imprese
Programming area
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Programme
- ROP CONV ERDF BASILICATA
- Axis
- Competitività produttiva
- Operational objective
- Realizzazione di opere d'infrastrutturazione primaria e secondaria per la piena fruibilità di aree attrezzate per insediamenti produttivi già attivi.
Other projects in territory
Same theme
LAVORI DI EFFICIENTAMENTO ENERGETICO DELLÂ IMPIANTO DI PUBBLICA ILLUMINAZIONE DELLA STRADA COMUNALE PANTANO | € 51,621 |