CUP: J43B12000530001
INTERVENTO INTEGRATO PER IL COMPLETAMENTO DELLE OPERE DI DIFESA COSTIERA E RICOSTRUZIONE DEL LITORALE (LITORALE DI PAOLA Â PORTO DI CETRARO) - ECI13
SUMMARY OF THE PROJECT
INTERVENTO INTEGRATO PER IL COMPLETAMENTO DELLE OPERE DI DIFESA COSTIERA E RICOSTRUZIONE DEL LITORALE (LITORALE DI PAOLA Â PORTO DI CETRARO)
Implementation indicator
Estensione in lunghezza
- Target
- 1 km
- Achieved
- 0 km
This project is eliminated from views and totals because it is a duplicate of the project:
Funding monitored
€ 4,000,000.00
of which cohesion funds
€ 4,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 4000000.00 |
Payments monitored
€ 3,560,077.30
of which cohesion funds
€ 3,560,077.30
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 5200.00 | 5200.00 | 0 |
2017 | 1132585.10 | 1137785.10 | 28 |
2018 | 1934186.30 | 3071971.40 | 76 |
2019 | 488105.90 | 3560077.30 | 89 |
State of progress
Open
Expected start: 30/10/2016
Effective start: 14/06/2017
Expected end: 28/02/2020
Effective end: 28/06/2019
Entities
- Planning body
- REGIONE CALABRIA
- Implementing body
- REGIONE CALABRIA
- Beneficiary
- REGIONE CALABRIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE CALABRIA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico